Building wrap and new windows
The whole building wrapped before new siding goes on.
Case study · Apartment community · Arlington, VA
Envelope replacementApartment community
Arlington, VA
Siding, windows, building wrap, insulation
2026
This four-story apartment building received a complete new building envelope. The work covered:
The community stayed occupied while the walls were open. Work areas were fenced and marked off, and crews worked from aerial lifts along the facades.
Each wall went back together in order: damaged sheathing replaced, insulation installed, building wrap applied, new windows and balcony doors flashed into the wrap, and new siding installed over it. That sequence is what keeps water out of the wall for decades, and it is the step most often rushed on a low bid.
During construction, fall 2026.

The whole building wrapped before new siding goes on.

Buildings in the community under envelope work at the same time.

New windows set in the wrap on the courtyard side.

Each opening is flashed into the weather barrier before siding.

Crews reach upper floors from lifts, not ladders.

Siding installed over the new building wrap.