What a building energy performance standard is
A building energy performance standard, or BEPS, sets a minimum energy performance level for existing buildings and requires buildings that fall short to improve within a set period. It builds on benchmarking, the annual reporting of energy use through ENERGY STAR Portfolio Manager that many larger buildings already do.
This is a summary for planning purposes. Requirements and deadlines change; check the current rules with the county or District agency and an energy professional for your specific building.
Montgomery County, Maryland
Montgomery County's BEPS covers most commercial and multifamily buildings of 25,000 gross square feet and larger. Buildings are grouped by type and size. Multifamily residential buildings of 250,000 gross square feet and more form one group, and multifamily buildings from 25,000 to 250,000 gross square feet form another.
According to the county's technical guidance, the larger multifamily group has interim and final performance deadlines at the end of 2030 and 2035, and the 25,000 to 250,000 square foot group at the end of 2031 and 2036. Owners that cannot meet the standard may use an approved Building Performance Improvement Plan that sets out the upgrades and timeline.
Washington, DC
The District's BEPS program, run by the Department of Energy and Environment (DOEE), applies to privately owned buildings above size thresholds that step down over successive periods. The first period covered private buildings of 50,000 square feet and more; later periods extend coverage to smaller buildings, first 25,000 square feet and later 10,000. Buildings below the standard enter a multi-year compliance cycle with several pathways, including performance and prescriptive options.
The timing of the next cycle has been adjusted by legislation. Recent guidance indicates DOEE will set the next cycle's standards on or before January 1, 2029, so owners of buildings between 25,000 and 50,000 square feet should keep benchmarking accurately and plan ahead.
Which upgrades usually move the numbers
Every building is different, and an energy audit should guide the decision. In multifamily and commercial buildings, the improvements that commonly matter most are:
- Replacing aging central plant or rooftop HVAC equipment with higher-efficiency systems and controls.
- Common-area and site lighting converted to LED with occupancy and daylight controls.
- Air sealing, insulation and window replacement during envelope projects.
- Domestic hot water system upgrades and pipe insulation.
- Retro-commissioning: tuning existing systems so they run as designed.
A practical first year
For a board or owner just starting to think about BEPS, a reasonable first year looks like this:
- Confirm coverage. Check whether the building is on the county or DOEE list of covered buildings and which group or period it falls into.
- Verify the data. Make sure benchmarking is complete and accurate, including all meters and common areas. Bad data can make a building look worse than it is.
- Commission an energy audit. An audit identifies which measures will reduce energy use in this specific building and roughly what each will cost.
- Overlay the capital plan. Compare the audit's recommendations with the reserve study and the five-year project schedule to find projects that can serve both purposes.
- Price efficient options. When a component such as a boiler, rooftop unit or lighting system comes due, ask contractors to price both a like-for-like and a high-efficiency replacement.
Owners often find that the gap to the standard can be closed with projects they would have done anyway, sequenced and specified with energy performance in mind.
Combine compliance with the reserve study
The most expensive way to comply is to treat BEPS as a separate project. Most of the upgrades above appear in reserve studies anyway, just under different names: HVAC replacement, lighting, windows, roofing. When those components come due, choosing the more efficient option and documenting the expected savings often costs little more than a like-for-like replacement and counts toward compliance.
A practical approach is to overlay the BEPS deadlines on the five-year capital plan, identify which scheduled projects affect energy use, and price an efficient option for each.
Sources: Montgomery County DEP: Building Energy Performance Standards · Montgomery County BEPS technical guidance (PDF) · Holland & Knight: DC BEPS update, October 2026
This article is general information, not legal advice.
Frequently asked questions
Does BEPS apply to our condominium?
In Montgomery County and DC, it depends mainly on building size and type, starting at 25,000 gross square feet for private buildings under current rules. Check your building’s benchmarking status with the county or DOEE.
What happens if a building does not meet the standard?
It enters a compliance cycle with time to improve, using one of the available pathways. Penalties can apply for buildings that do not comply by the end of the cycle.
Can capital projects count toward compliance?
Yes. Efficient replacements of HVAC, lighting, windows and other systems can reduce measured energy use; an energy professional can estimate the effect for your building.
Planning a project like this?
Tell us about the property. We walk the buildings and give the board a written report with options and prices.