Change orders explained: why hidden conditions are billed separately
Almost every renovation of an older building finds something nobody could see at bid time. The question is not whether hidden conditions will appear, but whether the process for handling them protects the association.
BuildWise team · November 2026 · 3 min read
What a hidden condition is
A hidden condition is damage or a deviation from expected construction that could not reasonably be seen before work started: rotted sheathing behind siding, a soft roof deck under shingles, corroded balcony connections inside a deck, or framing that does not match the original drawings. It is different from work the contractor simply forgot to include in the bid.
Because nobody knows the quantity in advance, there are only two honest ways to price it: an allowance or unit prices. Anything else means either the contractor guesses high and the association overpays, or the contractor guesses low and asks for more later.
Unit prices: the simplest protection
Ask every bidder to quote unit prices for the hidden conditions most likely on your project, for example per sheet of sheathing, per linear foot of rim board, per square foot of roof decking or per balcony joist. Compare these between bidders as carefully as the base price. When damage is found, the cost is quantity times an agreed price, with no negotiation in the middle of the job.
How a change order should be documented
A well-run change order process has four parts:
- Stop and photograph. The crew documents the condition before repairing it, with location and measurements.
- Notify. The project manager sends the photos and a written description to the manager or board contact the same day.
- Price. The change order states the quantity, the unit price from the contract and the total, plus any schedule impact.
- Approve before work. Nothing is billed without a signed change order, except genuine emergencies, which are documented the same way afterward.
For repetitive repairs, the board can pre-approve a not-to-exceed amount per building so work does not stall waiting for a meeting, with a running log reported weekly.
Budgeting a contingency
Even with unit prices, the board needs money set aside for what may be found. Older buildings and envelope or balcony work justify a larger contingency than, for example, repaving. The contractor's condition survey and test openings help size it: a few openings at suspect locations before bidding can turn a rough guess into a reasonable estimate.
Writing hidden conditions into the contract
The best time to settle how hidden conditions will be handled is before the contract is signed. A few clauses make most of the difference:
- A unit price schedule attached to the contract, covering the conditions most likely on the project.
- A definition of what counts as a hidden condition, so it is clear that items visible at bid time are part of the base price.
- Documentation requirements: photos before and after, location, quantity and a short description for every change.
- Approval authority: who can sign a change order for the association, and up to what amount, so work does not stop waiting for a meeting.
- Emergency provisions: what the contractor may do immediately to protect the building or residents, and how that work is documented and approved afterward.
- Schedule impact: whether a change order extends the completion date and by how much.
With these in place, a change order becomes a routine record rather than a negotiation. The board sees the same information for every change, the contractor knows what will be paid, and the final cost stays predictable.
Explaining change orders to owners
Owners accept additional cost when they can see why it was necessary. Keep the photos, share a summary at the next owners' meeting, and include the change order log in the project closeout file. It also becomes valuable information for the next reserve study.
Frequently asked questions
Is a change order a sign the contractor bid too low?
Not necessarily. Hidden conditions are a normal part of renovating occupied buildings. The concern is change orders for work that should have been in the original scope.
Can the board cap change orders?
Yes. A not-to-exceed amount per building or per phase, with weekly reporting, keeps work moving while limiting exposure.
What should we do if work was done without a signed change order?
Ask for the photos and documentation required by the contract, and discuss with the association’s attorney before paying for undocumented work.