Insights · Planning
How to hire a contractor for a condominium or HOA capital project
Choosing a contractor is one of the largest decisions a volunteer board makes. Here is a process that keeps the comparison fair, protects the reserves and holds up when owners ask how the decision was made.
BuildWise team · November 2026 · 4 min read
Start with the scope, not the bids
Most bid comparisons go wrong before the first contractor walks the property. If three companies price three different interpretations of "replace the siding," the lowest number tells the board nothing. The fix is a written scope that every bidder prices the same way.
A good scope for an association project answers five questions:
- What, exactly: the components, quantities and materials, taken from the reserve study and a site walk.
- Where and in what order: which buildings, which elevations, and whether the work is phased over one or several budget years.
- How residents are affected: work hours, parking closures, access to units, notice periods.
- What happens to hidden conditions: unit prices for rotted sheathing, framing or deck repairs, so surprises are priced before work starts.
- What the association receives at the end: warranties, photos, permits and closeout records.
If the board does not have an engineer or consultant writing specifications, ask the contractors on the short list to walk the property and submit a written condition report with their proposal. Comparing what each one noticed is often as revealing as comparing the price.
Build a short list you can actually check
Three to five qualified bidders is usually enough. More than that creates paperwork without improving the result. For each company, collect the same information before you invite them to bid:
- State contractor licensing appropriate to the scope and the jurisdiction where the property sits.
- Certificates of general liability and workers' compensation insurance, with the association listed as certificate holder.
- Three references from similar work: occupied buildings, associations or managed property, completed in the last few years.
- The name of the person who will run the job day to day, not only the salesperson.
Call the references and ask specific questions: Did the project finish on the schedule they promised? How were change orders handled? How did residents describe the crews? Would you hire them again for the next phase?
Compare bids line by line
Ask every bidder to price the scope in the same format, broken into line items. A single lump sum hides the differences that matter. When proposals come back, put them side by side in a spreadsheet and look for:
- Exclusions. Permits, dumpsters, scaffolding, protection of landscaping and debris removal are common places for a low bid to leave things out.
- Unit prices for hidden conditions. A bid with low unit prices for rot repair may end up cheaper than one with a lower base price.
- Schedule and crew size. A bid that finishes in half the time is either staffing the job differently or making an optimistic promise.
- Warranty. Compare both the manufacturer's material warranty and the contractor's workmanship warranty, and what voids them.
If a number is far below the others, ask the bidder to walk you through it. Sometimes it reflects a better method. Often it reflects a different scope.
Protect the association in the contract
The contract should match the scope the board approved and the proposal it accepted. Have the association's attorney review it, and make sure it covers at least:
- A payment schedule tied to completed, inspected work rather than to dates, with retainage held until closeout.
- A written change order process: no extra work without a signed change order that states the price and the reason, supported by photos.
- Insurance requirements for the duration of the job, including the association as additional insured where appropriate.
- Lien waivers with each payment, so the association is not exposed to claims from suppliers or subcontractors.
- Work hours, site rules and resident communication responsibilities.
- Closeout deliverables: warranties, final photos, permit sign-offs and a punch list walkthrough.
Make the decision easy to explain to owners
Owners rarely object to a project because of the contractor's name. They object when they do not understand why money is being spent or why one company was chosen. Keep a short decision memo with the scope, the bid comparison and the reasons for the selection. Share the schedule and the resident notice plan before work begins.
A contractor that works with associations regularly will help with this. Ask whether they will present the proposal at a board meeting and draft the notices residents receive before work starts. Those two things often determine how smoothly the project runs.
Frequently asked questions
How many bids should an HOA or condominium get?
Three to five qualified bids on the same written scope is usually enough. More bids add administrative work without making the comparison better.
Should the board always choose the lowest bid?
Not automatically. Compare exclusions, unit prices for hidden conditions, schedule and warranty. A bid that leaves out permits or rot repair can cost more by the end of the job.
Who writes the scope of work?
An engineer or consultant on larger projects. On smaller ones, a written condition report and scope from the contractors on the short list, compared side by side, can serve the same purpose.