Turning a reserve study into a five-year project plan

A reserve study tells the board what will wear out and roughly when. It does not tell you how to group, schedule or build the work. Here is how to get from one to the other.

BuildWise team · November 2026 · 7 min read

Key takeaways

  • The study’s years are estimates. A site survey tells you which items are really due.
  • Bundle components that share access, like roofs with gutters or siding with windows.
  • Spread work across budget years so the reserve balance never drops below the study’s plan.
  • Carry a contingency for what you cannot see until the old material comes off.
What the law requires

In Virginia, the Condominium Act and the Property Owners' Association Act require the board to have a reserve study done at least once every five years, to review it every year, and to adjust reserves as needed. Maryland requires condominiums, cooperatives and HOAs to update their study at least every five years; legislation passed in 2025 added a funding plan and ties annual reserve funding to the study's recommendation.

So most boards have a study. The harder question is what to do with it.

Read the study by condition, not just by year

A reserve study assigns each component a useful life and a remaining life. Those numbers are averages. A south-facing roof can fail years before the study says, and well-maintained siding can last longer. Before committing money, have the components due in the next five years surveyed on site and rated by actual condition.

Group components into projects

Studies list components one by one. Contractors build projects. Grouping components that share scaffolding, lifts or access saves the association money and residents disruption.

  • Roofing: shingles, underlayment, flashing, gutters and vents. One tear-off, one set of protections.
  • Envelope: siding, trim, sealants and windows. Windows are flashed into the new wall.
  • Site: paving, striping, sidewalks, curbs and lighting. One parking plan for residents.
Phase by budget year

Once projects are defined, place them on a five-year calendar against the reserve balance the study projects. Large projects can be split by building over two or three years. The goal is a schedule where the reserve balance stays at or above the study's funding plan each year, so the board avoids a special assessment.

Plan for hidden conditions

Some damage is invisible until old material comes off: rotted sheathing under siding, soft roof deck, corroded balcony connections. Ask contractors to price these as unit costs in the proposal, such as a price per sheet of sheathing, and carry a contingency in the budget. Any hidden work should be photographed and approved before it is done.

Bring owners along

Owners accept large projects when they understand them. Share the condition photos, explain why projects are grouped the way they are, and give residents written notice before work reaches their building.

Sources: Code of Virginia § 55.1-1965 · Maryland Chapter 519 (HB 292), 2025

This article is general information, not legal advice. Confirm requirements with the association's attorney.

Have a reserve study on the shelf?

Send it to us. We will turn the components that are due into a phased plan with prices.